PROGRAMME FOR DELIVERY

Feb
2017

Demolition commenced.

July
2017

Demolition works completed.

Apr
2018

Basement works complete.

July
2018

Concrete core complete.

Dec
2018

Frame complete.

Apr
2019

Access to shell and core for Category B works.

May
2019

Show floor complete. Commissioning and testing commences.

Summer
2019

Practical completion.